Approval procedure for passenger platforms located on third-party railway lines
Operators of passenger platforms* are generally required to have their proposed charges for the use of their passenger platforms approved. Under Annex 2 para 1(c) to the ERegG the use of railway infrastructure, including the use of passenger platforms and access routes, is part of the minimum access package, and the calculation of usage charges must comply with section 31a ERegG. The requirement that charges for the use of passenger platforms receive approval has its legal basis in section 31a(1) sentence 2 ERegG.
This approval requirement also applies to passenger platforms located on railway lines operated by third parties. If, pursuant to section 2a(5) ERegG, the railway lines on which the passenger platform is located do not fall under the scope of section 2a(1) ERegG, there is no exemption from section 34(3) ERegG for the passenger platform located on the railway line. The operator of the passenger platform must therefore comply with the requirements of section 10a(1) and (5) ERegG.
Pursuant to section 31a(2) sentence 2 ERegG, the approval is to be granted if the calculation of the charges meets the requirements of section 23(1) and (2) sentence 1, section 24(2) to (4) and sections 34 to 41 ERegG. Furthermore, pursuant to section 31a(1) sentence 1 ERegG, the charge for the minimum access package is to be shown in euros per instance of use, which is normally per stop at the passenger platform. In addition, pursuant to section 34(3) ERegG, the charge for the passenger platforms that are part of the minimum access package must be based on the direct costs of train operation. Beyond this, in order to cover the total costs, the operator of the passenger platform can levy markups on the direct costs of train operation in accordance with section 36(1) ERegG on the basis of efficient, transparent and non-discriminatory principles while guaranteeing optimal competitiveness of rail market segments. However, operators of passenger platforms have no obligation to cover full costs.
With regard to the formal approval procedure, section 31a(2) sentence 3 ERegG declares the requirements of section 46 ERegG to be applicable, except that instead of a deadline for submitting requests for train paths, a deadline can be set in the network statement for submitting requests for use, and the calendar year can also be used instead of the working timetable period. In addition, pursuant to section 46(4) ERegG, the approval must be granted for one working timetable period or one calendar year and must generally be limited to the end of a working timetable period or a calendar year.
It is possible to show the charge for passenger platforms located on third-party railway lines in the network statements for service facilities alongside the charges for the passenger station and the charges for station use on the operator’s own lines.
Before applying for charge approval, a comments procedure must be conducted in accordance with section 19(2) ERegG. For this purpose, the intended revision or modification must be published on the website of the operator of the passenger platform. The published draft must include a presentation of the modifications in an appropriate form, in particular as a synoptic representation, with the necessary explanations. The access beneficiaries must be given one month to comment on the revision or modification.
*Passenger platforms are the area of the rail network where passengers board and alight from the trains, including all equipment and structures that are not legally assigned to the operation of the passenger station (see definition in section 1(26) ERegG). An operator of a passenger platform is any operator of railway infrastructure that is responsible for the construction, the operation, the service and maintenance, and the renewal of passenger platforms including the access to these passenger platforms (see definition in section 1(5) ERegG